Weekly Report 19th April through 25th April

Status Meetings

We had status meetings on Monday (19 April) and Tuesday (20 April) and we discussed the current status of individual implementation efforts. The porting of the current version of the software was complete and we also had completed the parsers for loading and saving the dataflow and loading the module library. We also discussed the work needed to be done for the approaching final presentation. Individual portions of the final presentation were assigned.

Coding and Porting

The current version of dflow runs on Windows now. We also integrated the completed parsers into the main dflow program and we tested the loading and saving of different kinds of dataflows and loading a sample module library file.

We are confident of getting everything done by the final project presentation.