Smart Search Timeline

Project Start Date: Tue 1/19/99
Project Finish Date: Thu 4/22/99

ID Task_Name Duration Start_Date Finish_Date
1
Begin SmartSearch Project
1 day Tue 1/19/99 Tue 1/19/99
2
Meet with our Client (Bill Mark)
1 day Fri 1/22/99 Fri 1/22/99
3
Contract- Design & Construct
3 days Mon 1/25/99 Wed 1/27/99
4
Schedule- Planning/Revising
6 days Thu 1/28/99 Thu 2/4/99
5
Demo Beta
2 days Fri 1/29/99 Mon 2/1/99
6
User Manual - Initial version
10 days Mon 2/1/99 Fri 2/12/99
7
Find Lexical Analyzer
14 days Fri 2/5/99 Wed 2/24/99
8
Web Interface - (User Int)
5 days Mon 2/1/99 Fri 2/5/99
9
Design - General project req'ts
14 days Thu 2/4/99 Tue 2/23/99
10
Construct lexical input script
6 days Mon 2/8/99 Mon 2/15/99
11
Develop Categories and Web sites
3 days Thu 2/11/99 Mon 2/15/99
12
Integration of Lexical Analyzer
37 days Fri 2/12/99 Mon 4/5/99
13
Database Development
29 days Fri 2/12/99 Wed 3/24/99
14
Midterm Demo Prep
7 days Thu 2/18/99 Fri 2/26/99
15
User Manual - First Revision
3 days Tue 3/2/99 Thu 3/4/99
16
Technical Manual - Initial version
5 days Wed 3/3/99 Tue 3/9/99
17
Testing/Debugging parts
14 days Mon 3/29/99 Thu 4/15/99
18
Polishing/Golden master
12 days Mon 4/5/99 Tue 4/20/99
19
Final Demo Preparation
4 days Mon 4/19/99 Thu 4/22/99
20
Golden Master Packaged
2 days Mon 4/5/99 Tue 4/6/99