Weekly Report 4


Outstanding Problems
None

Plans to address outstanding problems
N/A

Hours Worked
Corie Burns
	?3 hours
     	?9 hours total
Sandy Hall
	?4 hours
	?9.5 hours total
        
Kamali Horton
	3 hours
	10 hours total
Sangwook Park
	3 hours
	8 hours total

Milestones
Accomplished
	Second client report
	Setup system environment such as MySQL, Linux and Perl by Joe
	Preliminary Report done
Approaching
	Write the contract version one
	Understand tools(Perl and MySQL) for project
Problems/slips and plans to address
	None