Weekly Report
B a c k 
  • Week 11
  • March 21st, 2001 through March 26th, 2001
  • Report By: Karen Parker
  • Attendees: Karen, Brianne, Sean, Jason
  • Action items
    • Closed:
      • We now have a folder set up on the FLRC domain for our use.
      • The template for the lyrics needs to be in HTML format. This file should be created outside of Word to eliminate the embedded XML.
      • Saving of state using Sean's code has been integrated into the existing code.
    • Residual:
      • Word and Graphics sections need to be finished ASAP.
      • Graphics section only needs the graphic to be saved and for the special notes appended to the total notes file.
      • Lyrics phase is not completed at all.
      • Make the modification screen a drop down box of the files for the user to choose instead of typing in the lesson name by memory.
    • New:
      • Everyone will be working on the first phase to get it caught up before moving to the next phase.
      • Final Deadline to get this phase complete: April 2-3.
      • The "Next" button needs to have the enter key implemented.
      • Flag for determining creation vs. modifications for "Next" button.
      • An extra form will be needed for the audio extraction screen to eliminate the user from having to re-extract audio if not in modification.


  • Outstanding problems
    • We are not on schedule.


  • Plans to address outstanding problems
    • A new schedule has been created to accommodate for finishing the first phase.


  • Hours worked for each team member
    • This week:
      • Karen Parker: 20
      • Brianne Roth: 10
      • Sean Rielly: 10
      • Jason Howell: 20
      • Sam Adu: NA
    • Total so far:
      • Karen Parker: 133
      • Brianne Roth: 86
      • Sean Rielly: 108
      • Jason Howell: 132
      • Sam Adu: 15


  • Milestones (schedule status)
    • Accomplished:
      • Phase one is almost complete.
      • We now have the FLRC folder for testing.
    • Approaching (next week):
      • Finish phase one ASAP.
      • Beta to be launched in 2 weeks!
    • Problems/slips and plans to address:
      • New schedule made.