Project Start Date: Tue 1/16/01
Project Finish Date: Fri 5/4/01

Who Does What

Resources and Assignments
StartFinishWork
Unassigned
Tue 2/6/01Tue 5/1/010 hrs
Backbone Milestone
Wed 4/4/01Wed 4/4/010 hrs
Beta Version Deployed
Tue 4/17/01Tue 4/17/010 hrs
Beta Deployment
Tue 4/17/01Fri 4/20/010 hrs
Beta Report from Dick
Fri 4/20/01Fri 4/20/010 hrs
Final Revisions
Mon 4/23/01Fri 4/27/010 hrs
Final Product Available
Mon 4/30/01Mon 4/30/010 hrs
User Manual
Tue 2/6/01Wed 2/14/010 hrs
Implementation Manual
Tue 2/6/01Wed 2/14/010 hrs
Schedule II
Tue 2/13/01Tue 2/13/010 hrs
User Specification/Schedule III
Tue 2/20/01Tue 2/20/010 hrs
User Manual I
Tue 2/27/01Tue 2/27/010 hrs
Group Status Reports
Thu 3/1/01Thu 3/8/010 hrs
Class Presentation
Thu 3/1/01Thu 3/8/010 hrs
Prototype
Thu 3/1/01Thu 3/8/010 hrs
Implementation Manual
Tue 4/24/01Tue 5/1/010 hrs
User Manual II
Tue 4/24/01Tue 5/1/010 hrs
Karen
Tue 1/23/01Fri 5/4/01587 hrs
GUI Phase/VB Learning
Wed 2/7/01Mon 2/12/0135 hrs
Intro and Naming Phase
Tue 2/20/01Mon 3/5/0191 hrs
Audio Extraction Phase
Tue 3/27/01Tue 4/17/01149 hrs
Communication Phase
Tue 3/6/01Wed 4/4/01203 hrs
Packaging Phase
Fri 4/27/01Mon 4/30/0121 hrs
Documentation Phase
Tue 2/6/01Wed 2/14/0156 hrs
Preliminary Report
Tue 1/23/01Thu 1/25/018 hrs
Contract I
Tue 2/6/01Tue 2/6/010 hrs
Schedule I
Tue 2/6/01Tue 2/6/010 hrs
Contract II
Sun 2/11/01Tue 2/13/018 hrs
Project Packages
Wed 5/2/01Fri 5/4/018 hrs
Reports (Team, Individual)
Wed 5/2/01Fri 5/4/018 hrs
Sean
Tue 2/6/01Thu 5/3/01897 hrs
GUI Phase/VB Learning
Wed 2/7/01Mon 2/12/0135 hrs
Lyrics Text Phase
Tue 2/20/01Wed 4/4/01301 hrs
Audio Extraction Phase
Tue 3/6/01Tue 4/17/01296 hrs
Additonal Features Phase
Wed 3/21/01Tue 4/17/01185 hrs
Documentation Phase
Tue 2/6/01Wed 2/14/0156 hrs
Contract I
Tue 2/6/01Tue 2/6/010 hrs
Contract II
Sun 2/11/01Tue 2/13/018 hrs
Project Packages
Wed 5/2/01Thu 5/3/018 hrs
Reports (Team, Individual)
Wed 5/2/01Thu 5/3/018 hrs
Brianne
Wed 2/7/01Thu 5/3/01677 hrs
GUI Phase/VB Learning
Wed 2/7/01Mon 2/19/0184 hrs
Intro and Naming Phase
Tue 2/20/01Mon 3/5/0191 hrs
Modify Feature Phase
Mon 3/5/01Tue 4/17/01301 hrs
Additonal Features Phase
Wed 3/21/01Tue 4/17/01185 hrs
Project Packages
Wed 5/2/01Thu 5/3/018 hrs
Reports (Team, Individual)
Wed 5/2/01Thu 5/3/018 hrs
Jason
Tue 1/23/01Fri 5/4/01579.17 hrs
GUI Phase/VB Learning
Wed 2/7/01Mon 2/12/0135 hrs
Graphics Phase
Tue 2/20/01Wed 2/21/0113 hrs
Lyrics Text Phase
Tue 2/20/01Wed 4/4/01301 hrs
Modify Feature Phase
Sat 3/24/01Thu 4/12/01131.95 hrs
Packaging Phase
Fri 4/27/01Fri 4/27/012.2 hrs
Documentation Phase
Tue 2/6/01Wed 2/14/0156 hrs
Project WEB I
Tue 1/23/01Thu 1/25/018 hrs
Project WEB II
Tue 2/20/01Thu 2/22/018 hrs
WEB complete
Wed 5/2/01Fri 5/4/018 hrs
Project Packages
Wed 5/2/01Thu 5/3/018 hrs
Reports (Team, Individual)
Wed 5/2/01Thu 5/3/018 hrs
Sam
Wed 2/7/01Thu 5/3/01954 hrs
GUI Phase/VB Learning
Wed 2/7/01Mon 2/19/0184 hrs
Graphics Phase
Tue 2/20/01Wed 4/4/01285 hrs
Communication Phase
Tue 3/6/01Wed 4/4/01203 hrs
Testing/Quality Assurance
Mon 3/5/01Fri 4/27/01366 hrs
Project Packages
Wed 5/2/01Thu 5/3/018 hrs
Reports (Team, Individual)
Wed 5/2/01Thu 5/3/018 hrs