WEEKLY REPORT

WEEK # 10 (March 6 - March 22) {includes spring break}

 

Written by Melissa Chadburn, Producer

 

Action Items

 

 

New Items

Person Responsible

Deadline

Additional Notes

 

Schedule team meeting with Prof. Welch

 

 

Bill

 

03/23/2001

 

Prefer to meet as a team on Friday.

Topics:

(1)     Server issues

(2)     User Manual feedback, per suggestion in class on 3/20.

 

 

Send new User Manual Link to Prof. Welch

 

 

 

Jill

 

03/22/2001

 

Make additional link in our library (currently resides under works in progress)

Residual Items

Person Responsible

Deadline

Additional Notes & Results to Date

 

(D.1) ASP coding

 

 

Scott, Heather

 

 

04/03/2001

 

Work is progressing smoothly. Working with Javascript menu bar. ODBC connection is working properly. Still working on server issues which will determine whether ASP 2.0 (NT server) or ASP 3.0 (2000 server) can be used. Still to decide on use of SQL within ASP or use of access queries/reports.

 

 

(D.2 & D.3) Authentication Implementation

 

 

 

Bill

 

03/27/2001

 

In progress. D.2, D.3 expected complete date 03/26

 

Database Population

 

 

Jill, Melissa

 

03/29/2001

 

Database population of the first lesson to be completed using a cut & paste technique. Incorporating html tags into memo fields to maintain color coding in final ASP pages.

 

Closed Items

Person Responsible

Date

Completed

Additional Notes & Results

 

User Manual I

 

 

Melissa, Bill

 

03/08/2001

 

Complete. http://www.cs.unc.edu/~chadburn/145/145-15-UMI.doc

 

Weekly Report (week #10)

 

 

Melissa

Jill

 

03/22/2001

midnight

 

Email to Jill to post to web.

Jill: Email professor with URL.

 

 

Weekly Meeting Minutes

 

 

Scott

 

03/22/2001

midnight

 

Compiled and posted to project library.

 

 

 

Outstanding problems

 

       Server: We still do not have the windows 2000 server. Bill met with Jason (IS foreign languages) who told us we could not have access to develop on a server because we are undergraduate students. He suggested they would take control of the server and every request would be implemented by him or his team (Jason, that is). This includes adding tables to databases, etc! This is obviously not a feasible solution.

 

 

Plans to address outstanding problems

 

       Server: Bill will arrange a meeting with Prof. Welch. We will also discuss alternatives at our next client meeting scheduled for Monday, March 26th.

 

 

Hours worked FOR EACH TEAM MEMBER (does not include time in class)

 

 

Team Member

This Week

(March 6 March 22)

Total to Date

(January 15 March 22)

Melissa Chadburn

8.5

72.0

Heather Morgan

7.0

63.5

Scott Phillips

9.0

58.5

Bill Safcik

11.0

71.0

Jill Struble

6.0

49.0

 

Milestones This Week (schedule status)

 

Accomplished

Additional Notes

 

User Manual I

 

 

http://www.cs.unc.edu/~chadburn/145/145-15-UMI.doc

Approaching

 

 

Authentication Implementation

 

 

Due 03/27/2001. {Bill }

 

Database Population

 

 

Due 03/29/2001. { Jill, Melissa }

 

ASP development

 

 

Due 04/03/2001 {Heather, Scott }

Problems/ slips

Plans to Address

 

These slips present no threat to the project, we will still complete at a minimum phase I of plan A.

 

 

Slip ASP coding

New deadline:

04/03/2001

 

Our coding is taking longer than planned. Partly due to under-estimation of time needed to actually code and partly due to transferring development from SN to another pc (this is not the server migration referred to in the project schedule).

 

 

Slip Database Population

New deadline:

03/29/2001

extended 2 days

 

 

Population will be done via a cut and paste technique. Color coding will be maintained using html tags embedded in the access memo fields.