WEEKLY REPORT

WEEK # 12 (March 29 - April 3)

 

Written by Melissa Chadburn, Producer

 

Action Items

 

 

New Items

Person Responsible

Deadline

Additional Notes

 

No new items this week. Continue development as per the schedule

 

Residual Items

Person Responsible

Deadline

Additional Notes & Results to Date

 

Help Session Coding

 

 

Jill,

Melissa

 

04/10/2001

 

Will be developed in Publisher or Front Page. Does not need to be ASP. Heather to revise menu bar to open new browser window when help session is launched so that students do not lose their place in the tutorial, pre-test, or post-test.

 

 

DB Testing

 

 

Heather, Jill, Melissa

 

 

04/10/2001

 

Heather is keeper of all test data. Melissa/ Jill to document tests performed. Heather to verify.

 

(D.1) ASP coding

 

 

Heather,

Scott

 

 

04/10/2001

 

Heather and Scott will email the team when site is ready for review. Team will review prior to week 13 team meeting for the final vote/ approval.

 

 

Implementation Manual

 

 

Bill (lead)

Other to be determined

 

 

04/24/2001

 

Bill to include specifics about installation procedures due to delivery method change (ZIP, TAR, or other compressed format)

 

User Manual

 

 

Jill,

Melissa

 

 

04/24/2001

 

Jill and Melissa assigned to complete User Manual with input from other team members.

Closed Items

Person Responsible

Date

Completed

Additional Notes & Results

 

Update Client on Product Delivery

 

 

Team

 

04/02/2001

 

Discussed at the client meeting. Agreeable to client. **Installation and functionality will be documented in the implementation manual.

 

 

Weekly Report (week #12)

 

 

Melissa

Jill

 

04/03/2001

midnight

 

Email to Jill to post to web.

Jill: Email professor with URL.

 

 

Weekly Meeting Minutes

 

 

Scott

 

04/03/2001

midnight

 

Compiled and posted to project library.

 

 

Outstanding problems

       None

 

 

Plans to address outstanding problems

       N/A

 

 

Hours worked (does not include time in class)

 

 

Team Member

This Week

(March 29 April 3)

Total to Date

(January 15 April 3)

Melissa Chadburn

7.0

87.0

Heather Morgan

15.0

93.5

Scott Phillips

15.0

79.5

Bill Safcik

6.0

86.0

Jill Struble

5.0

63.0

Team Total

48.0

409.0

 

Milestones This Week (schedule status)

 

Accomplished

Additional Notes

 

N/A

 

Problems/ slips

Plans to Address

 

D.1 Team Vote

 

 

Delayed until next team meeting. Team will review individually and send change requests to Heather or Scott. Final vote for team approval is scheduled for 04/10/2001.

 

 

D.2 & D.3 Team Vote

 

 

Bills PC crashed so we cannot look at the authentication until tomorrow. The vote is delayed until the next team meeting. Team will review individually and send comments to Bill. Final vote for team approval is scheduled for 04/10/2001.

 

 


Schedule (Incomplete Items)