Action Items

 

 

PLEASE NOTE: There will be no weekly report next week due to spring break.

 

New Items

Person Responsible

Deadline

Additional Notes

 

User Manual I

 

 

Melissa, Bill

 

03/08/2001

 

To compile based on notes. Will send to Jill to post to web and email professor the url.

 

 

Review Test Plan

 

 

All

 

03/20/2001

 

Responses to Heather by next team meeting. http://www.unc.edu/~morganh/145/testplan.html

 

Residual Items

Person Responsible

Deadline

Additional Notes & Results to Date

 

(D.1) ASP coding

 

 

Scott, Heather

 

 

03/27/2001

 

Work is progressing. Continue to code ASP lesson pages (pre-test, post-test)

 

 

(D.2 & D.3) Authentication Implementation

 

 

 

Bill

 

03/27/2001

 

In progress. Look at IP (25.24.22.169) /userauth to see the current design. Predecessor to ASP login and logout development (D.2, D.3).

 

Database Reports and Queries for ASP pages

 

 

Jill, Melissa

 

03/27/2001

 

Database tables have been created. Reporting and queries for ASP are still in progress. Data population has been extended based on complications.

Closed Items

Person Responsible

Date

Completed

Additional Notes & Results

 

Client Update

 

 

Scott

 

03/06/2001

 

  • Request server update
    • The server is being set up this week and will be ready by the time we return from break.
  • Request contact person for program questions (especially *.pix files)
    • Received information from contact, Dr. Carson
    • We will likely acquire resources to manually enter information (or cut and paste)
  • Request feedback regarding publisher file
    • Received a word document outlining his requests and have complied via the prototype.

 

 

Prototype/ Presentation

 

 

Bill

Jill, Melissa

Scott, Heather

 

03/01/2001

 

Administration static html.

Tutorial static html, Sample grade/ timing page if time permits.

Pre & Post Test ASP/ static html.

Bill to put web pages on his server.

 

 

Testing Plan

 

Heather

 

02/27/2001

 

http://www.unc.edu/~morganh/145/testplan.html

 

 

Weekly Report (week #9)

 

 

Melissa

Jill

 

03/07/2001

midnight

 

Email to Jill to post to web.

Jill: Email professor with URL.

 

 

 

 

Outstanding problems

 

       Database population: Cut and paste technique may reduce time and resources required to populate the database.

       Server: Final server not ready yet. This may delay testing.

 

 

Plans to address outstanding problems

       Database population: Expect to be put in contact with a previous programmer.

       Server: Professor Domnguez has allocated his office space for our use. The pc is to be set up this week and will be operational by the time we return from the break.

 

 

Hours worked FOR EACH TEAM MEMBER (does not include time in class)

 

 

Team Member

This Week

(February 27 March 6)

Total to Date

(January 15 March 6)

Melissa Chadburn

3.0

63.5

Heather Morgan

11.0

56.5

Scott Phillips

8.0

49.5

Bill Safcik

7.0

60.0

Jill Struble

4.0

43.0

 

Milestones This Week (schedule status)

 

Accomplished

Additional Notes

 

Prototype /Presentation

 

 

Presentation completed March 1, 4:00 4:15 in Sitterson 011

Approaching

 

 

User Manual I

 

 

Due 03/08/2001

Problems/ slips

Plans to Address

 

D.1 D.3 and Database query/reporting

 

Our coding is taking longer than planned. Partly due to under-estimation of time needed to actually code and partly due to transferring development from SN to another pc (this is not the server migration referred to in the project schedule).

 

There is no threat to the project, we will still complete at a minimum phase I of plan A.