The two schedules are quite different:
0 1 2 3 4 5 6 7 8 9 10 11
GPS schedule:
.5 x 4 = (2)
.25 x 4 = (1)
.25 x 4 = (1)
2/3 x 6 = (4)
1/3 x 6 = (2)
f31
f11
f21
The new schedule:
.5 x 4 = (2)
.25 x 4 = (1)
.25 x 4 = (1)
1/2 x 6 = (3)
1/2 x 6 = (3)
0 1 2 3 4 5 6 7 8 9 10 11